IRImplementing rule
UAM.OP.VCA.191Fuel/energy scheme – fuel/energy planning and fuel/energy in-flight replanning
The IAM operator shall ensure that:
(a)the VCA carries a sufficient amount of usable fuel/energy and reserves to safely complete the planned flight and to allow for deviations from the planned operation;
(b)the planned amount of usable fuel/energy for the intended flight is based on all the following:
(1)fuel/energy consumption data provided in the AFM or current aircraft-specific data derived from a fuel/energy consumption monitoring system;
(2)the conditions under which the flight is to be operated, including but not limited to:
(i)performance required for the intended flight to the destination, including vertiports, diversion locations or operating sites, selected along the route;
(ii)anticipated masses;
(iii)NOTAMs;
(iv)anticipated meteorological conditions;
(v)the effects of deferred maintenance items in accordance with the IAM operator’s MEL and/or of configuration deviations in accordance with the IAM operator’s CDL;
(vi)the expected departure and arrival routing, and anticipated delays;
(3)the efficiency and capacity of energy storage devices for the planned operating conditions, considering degradation of those energy storage devices as appropriate;
(c)the pre-flight calculation of the usable fuel/energy and reserves for a flight includes:
(1)taxi fuel/energy that shall not be less than the amount expected to be used prior to take-off;
(2)trip fuel/energy that shall be the amount of fuel/energy that is needed to enable the aircraft to fly from take-off, or from the point of in-flight replanning, to landing at the destination vertiport, diversion location or operating site, taking into account the operating conditions of point (b)(2);
(3)contingency fuel/energy that shall be the amount of fuel/energy needed to compensate for unforeseen factors that could have an influence on the fuel/energy consumption to the destination vertiport, diversion location or operating site;
(4)final reserve fuel/energy that shall be determined based on all the following:
(i)a representative time provided in the AFM to perform a go-around from a landing decision point (LDP) and back to that LDP taking into account the certified minimum performance (CMP) of the VCA;
(ii)conservative ambient conditions from the point of view of fuel/energy consumption;
(iii)an appropriate configuration/speed to perform the go-around and approach procedures;
(iv)a conservative fuel/energy consumption;
(5)additional fuel/energy that shall be the amount of fuel/energy to enable the VCA to perform a safe landing at a vertiport, diversion location or operating site, selected along the route, taking into account the CMP of the VCA at any point of the route; this additional fuel/energy is required only if the amount of fuel/energy that is calculated according to points (c)(2) and (c)(3) is not sufficient for such event;
(6)extra fuel/energy to take into account anticipated delays or specific operational constraints; and
(7)discretionary fuel/energy, if required by the PIC;
(d)if a flight must proceed along a route or to a destination vertiport, diversion location or operating site other than that originally planned, in-flight replanning procedures for calculating the required usable fuel/energy include those referred to in point (b)(2) and in points (c)(2) to (6).
IR · UAM.OP.VCA.191 — Regulation (EU) No 965/2012 · Regulation (EU) 2024/1111 · Air OPS Easy Access Rules · EAR revision 27 Mar 2026