VERIFICATION OF COMPLIANCE
(a)Upon receipt of an application for a certificate, the Competent Authority should:
(1)nominate an individual to become the focal point for all aspects of the applicant’s certification process, and to coordinate all necessary activities, including the Competent Authority’s certification team. The nominated person should be responsible to the responsible person of the Competent Authority for confirming that all appropriate inspections and audits have been carried out. He/she should also ensure that the necessary prior approvals required are issued in due course;
(2)verify if the application shows compliance with the applicable requirements. The Competent Authority should also arrange for the steps to be followed during the certification process. This would, normally, start with the demonstration of compliance of the aerodrome with the established and notified certification basis (see AMC2 ADR.AR.C.015(c)) which will require the conduct of technical inspections by the Competent Authority and/or examination of submitted documentation, the participation to demonstrations, or tests conducted by the applicant, as the case may be, and the Competent Authority determines appropriate. This should also include the cases where the certification basis includes provisions for which the Competent Authority has accepted the applicant to demonstrate an equivalent level of safety to, or cases of special conditions, as applicable; If the Competent Authority is not satisfied with the outcome of the demonstration process for any elements of the certification basis, it should notify the applicant in writing. At the end of this phase, the Competent Authority should have documented evidence that the aerodrome meets the notified certification basis;
(3)review the aerodrome manual, which should be prepared in accordance with ADR.OR.D.005, and any other documentation provided by the applicant; and
(4)verify compliance with the applicable requirements of Part-ADR.OR, Part-ADR.OPS, as well as any other applicable requirement. When verifying compliance with such requirements, an audit should be conducted covering the following areas:
(i)compliance shown by the applicant with the applicable requirements of Part-ADR.OPS, or any other applicable requirements;
(ii)the applicant’s management system and its organisation, including: detailed management structure, including names and qualifications of nominated personnel; adequacy of the organisation and management structure, including allocated resources and numbers of personnel allocated by the applicant to key management tasks and other positions. Care should be taken to verify that the system is comprehensive, and is likely to be effective. Of particular importance is a careful review of the qualifications of the applicant’s nominated persons. Account should be taken of the relevance of the nominee's previous experience and known record;
(iii)safety management and compliance monitoring with applicable requirements;
(iv)documentation on which the certificate should be granted (organisation documentation as required by Part-ADR.OR, including technical manuals, such as the aerodrome manual etc.); and
(v)adequacy of facilities with regard to the applicant’s scope of work.
(5)in case of non-compliance, the applicant should be informed, in writing, of the corrections or supplements which are required.
(b)The Competent Authority should be satisfied with the demonstration of compliance of the aerodrome manual with the requirements referred to in ADR.OR.E.005 and the related AMCs.
(c)The Competent Authority should ensure that standardised and approved methods and tools are used by its personnel during the process described in paragraph a.
(d)In cases where an application for a certificate is refused, the applicant should be informed of the right of appeal existing under national regulations.
(e)Prior to issuing the certificate(s), the Competent Authority may require the conduct of one or more flights at the aerodrome, as well as any other test, or exercise it finds necessary.
(f)When the verification process is complete, the Competent Authority should issue the certificate(s) and ensure the publication of the certification status of the aerodrome in the aeronautical information publication (AIP).