MONITORING, OVERSIGHT AND CONTROL OF WORKS
(a)The aerodrome operator should hold prior to start-up and during the works regular site meetings to ensure that safety requirements are met and possible conflicts between the works and operations are resolved. Meetings should be documented. The following points should be considered:
(1)safety awareness in relation to work on the movement area;
(2)protection of construction workers from aerodrome hazards, including jet blast;
(3)procedure for quickly summoning emergency responders in case of a fire, spill, accident or similar event; and
(4)operational briefings on the interaction of the works with the aerodrome operations (e.g. runway(s) in use, expected visibility conditions, meteorological conditions, safety issues).
(b)The worksite control procedure established by the aerodrome operator should include, but not be limited to, the following elements:
(1)all contractor’s drivers should be escorted by a qualified vehicle operator or undergo appropriate driver training and testing in accordance with point ADR.OPS.B.024;
(2)access routes should be agreed upon in advance and clearly identified to minimise interference with operations on the aerodrome;
(3)possible changes to the existing road layout depending on the vehicle traffic levels;
(4)designation of staff access routes and if such routes do not exist, then a safety risk assessment should be conducted to ensure that access can be safely achieved;
(5)hours of operation of the works;
(6)any service clearance checks (underground location of services) that need to be undertaken before work commences to ensure that cables or pipes are not damaged;
(7)smoking restrictions;
(8)description, monitoring and enforcement of hot work restrictions (possibly involving a separate hot works permit);
(9)the requirement to use lookouts and/or listening watch on the appropriate ATS frequency, if required;
(10)if cranes are used, appropriate lighting and operating height restrictions to avoid infringement of obstacle limitation surfaces, obstacle protection surfaces, interference with radio navigation aids, surface movement radar and line of sight of ATS tower;
(11)procedures for crossing taxiways, if required;
(12)adequate FOD and dust control measures that should be taken by all contractors to cover all eventualities;
(13)requirement for vehicles entering or leaving the worksite to be cleaned to prevent mud or debris being deposited in the movement area;
(14)provision of an appropriate alerting mechanism to suspend work activities, in case of possible adverse meteorological conditions (e.g. lightning strikes, strong winds, snow, low visibility) or aircraft emergencies;
(15)measures to ensure that worksite floodlighting (light direction and/or height) does not affect aircraft and ATS operation.
(c)Where significant changes to markings or lightings are being made, the aerodrome operator should conduct a preliminary check to ensure that the changes have been correctly implemented and are functioning as intended.
(d)The aerodrome operator should obtain feedback from the parties involved to ensure the implementation of corrective actions, if necessary.
(e)The aerodrome operator should ensure that contractors have made available a point-of-contact outside normal working hours.