(a)Contracted activities include all activities within the organisation’s scope of approval that are performed by another organisation either itself certified to carry out such activity or if not certified, working under the contracting organisation’s approval. The organisation shall ensure that when contracting or purchasing any part of its activity, the contracted or purchased service or product conforms to the applicable requirements.

(b)When the certified organisation contracts any part of its activity to an organisation that is not itself certified in accordance with this Part to carry out such activity, the contracted organisation shall work under the approval of the contracting organisation. The contracting organisation shall ensure that the competent authority is given access to the contracted organisation, to determine continued compliance with the applicable requirements.

IR · ORA.GEN.205 — Regulation (EU) No 1178/2011 · Regulation (EU) No 290/2012 · Aircrew Easy Access Rules · EAR revision 25 Nov 2025

AMCAcceptable means of compliance

AMC1 ORA.GEN.205Contracted activities

Show the text

RESPONSIBILITY WHEN CONTRACTING ACTIVITIES

(a)The organisation may decide to contract certain activities to external organisations.

(b)A written agreement should exist between the organisation and the contracted organisation clearly defining the contracted activities and the applicable requirements.

(c)The contracted safety related activities relevant to the agreement should be included in the organisation's safety management and compliance monitoring programmes.

(d)The organisation should ensure that the contracted organisation has the necessary authorisation or approval when required, and commands the resources and competence to undertake the task.

AMC · AMC1 ORA.GEN.205 — Regulation (EU) No 1178/2011 · ED Decision 2012/007/R · Aircrew Easy Access Rules · EAR revision 25 Nov 2025

GMGuidance material

GM1 ORA.GEN.205Contracted activities

Show the text

RESPONSIBILITY WHEN CONTRACTING ACTIVITIES

(a)Regardless of the approval status of the contracted organisation, the contracting organisation is responsible to ensure that all contracted activities are subject to hazard identification and risk management as required by ORA.GEN.200(a)(3) and to compliance monitoring as required by ORA.GEN.200(a)(6).

(b)When the contracted organisation is itself certified to carry out the contracted activities, the organisation’s compliance monitoring should at least check that the approval effectively covers the contracted activities and that it is still valid.

(c)If the organisation requires the contracted organisation to conduct an activity which exceeds the contracted organisation’s terms of approval, this will be considered as the contracted organisation working under the approval of the contracting organisation.

GM · GM1 ORA.GEN.205 — Regulation (EU) No 1178/2011 · ED Decision 2012/007/R · Aircrew Easy Access Rules · EAR revision 25 Nov 2025

All rules in SUBPART GEN – GENERAL REQUIREMENTS

Consolidated from the EASA Easy Access Rules (revision 25 Nov 2025, extracted 17 Aug 2026) for convenience. Not the official publication — verify against the Official Journal of the European Union and the EASA publications before operational use.

Ask Metis about ORA.GEN.205 →

Metis opens with Avioverse in October 2026 · request early access.