AMCAcceptable means of compliance
AMC1 SPA.SETIMC.105(a) SET-IMC operations approval
AMC1 SPA.SET-IMC.105(a) SET-IMC operations approval
TURBINE ENGINE RELIABILITY
(a)The operator should obtain the power plant reliability data from the type certificate (TC) holder and/or supplemental type certificate (STC) holder.
(b)The data for the engine-airframe combination should have demonstrated, or be likely to demonstrate, a power loss rate of less than 10 per million flight hours. Power loss in this context is defined as any loss of power, including in-flight shutdown, the cause of which may be traced to faulty engine or engine component design or installation, including design or installation of the fuel ancillary or engine control systems.
(c)The in-service experience with the intended engine-airframe combination should be at least 100 000 h, demonstrating the required level of reliability. If this experience has not been accumulated, then, based on analysis or test, in-service experience with a similar or related type of airframe and turbine engine might be considered by the TC/STC holder to develop an equivalent safety argument in order to demonstrate that the reliability criteria are achievable.
AMC · AMC1 SPA.SET — Regulation (EU) No 965/2012 · ED Decision 2017/004/R · Air OPS Easy Access Rules · EAR revision 27 Mar 2026