IRImplementing rule
CS 26.301Compliance plan for (R)TC holders and applicants
Compliance with point 26.301 of Part-26 is demonstrated when a compliance plan exists that includes the following:
(a)a project schedule identifying all the major milestones for meeting the compliance dates as specified in points 26.302 to 26.309 of Part-26, as applicable;
(b)a proposed means of compliance with the applicable requirements as specified in points 26.302 to 26.309 of Part-26, including as appropriate, methods and procedures for:
(1)performing the damage tolerance evaluation (DTE) of baseline structure, modified structure and published repairs;
(2)identifying the aeroplane structural configuration to be evaluated;
(3)identifying widespread fatigue damage (WFD)-susceptible structure;
(4)identifying the source of engineering data that will be used to perform the required evaluations;
(5)performing the WFD evaluation of structure;
(6)establishing a limit of validity (LOV) and plans for distribution upon approval (including incorporation of the LOV into the (airworthiness limitation section) ALS);
(7)identifying and developing the maintenance actions required to support the LOV;
(8)developing a baseline corrosion prevention and control programme (CPCP);
(9)establishing a process to ensure the continuing structural integrity programme remains valid;
(10)establishing the list of fatigue-critical baseline structures (FCBSs);
(11)developing the repair evaluation guidelines (REGs);
(c)a plan for submitting a draft of all the required compliance items for review by EASA not less than 60 days before the applicable compliance date.
[Issue: 26/3]